7.3 Control Costs

 

Back to Process Group Mappings

7.3 Control Costs

The process of monitoring the status of the project to update the project budget and managing changes to the cost baseline.

 

Simple Version: Monitor, record and analyze the project spend and forecasts.

PMI

 

Agile

PMBOK, Agile Difference, Comment

Inputs

Project management plan

Project funding requirements

Work performance information

Organizational process assets

 

Tools and Techniques

Earned value management

Forecasting

To-complete performance index (TCPI)

Performance reviews

Variance analysis

Project management software

 

Outputs

Work performance measurements

Budget forecasts

Organizational process assets updates

Change requests

Project management plan updates

Project document updates

 

Inputs

Project management plan

Project funding requirements

Work performance information

Organizational process assets

 

Tools and Techniques

Earned value management

Forecasting

To-complete performance index (TCPI)

Performance reviews

Variance analysis

Project management software

 

Outputs

Work performance measurements

Budget forecasts

Organizational process assets updates

Change requests

Project management plan updates

Project document updates

 

Feedback from early iterations on velocity, change rates and defect densities are analysed to see how feasible the estimates are.

 

Services

  • Books and Products
  • Training Courses

Extras

  • Spreading Agile to the PMI
  • Articles as PDF Documents
  • PMBOK vs to Agile Process Mappings

Contact

  • Contact Mike
  • Suggest a Topic

Subscribe

* indicates required

Recent Posts

  • PMI-ACP Supported Self-Study Group - February 2021 Start
  • Navigating Complexity: Zoom Towns and the 'K' Shaped Recovery
  • Illuminating the Intangibles of Agile
  • A New Litmus Test for Agile in 2020
  • Agile Communications Plans
  • Project Communication: Why Is It So Hard?
  • Adapting to All-Remote Talent Management
  • Inside the PMP Question Writing Process
  • The Perfect Storm for The Project Economy
  • Estimating Agile Projects...Or Not

Categories

  • Agile Project Management
  • Books
  • Certification
  • Estimating
  • Events
  • Exceptions
  • Games
  • Leadership
  • Lean
  • Metrics
  • NoProjects
  • Personal Agility
  • Planning
  • PMI-ACP
  • Remote Work
  • Retrospectives
  • Risk Management
  • Tailoring Approaches
  • Teams
  • Theory of Constraints
  • Travel
  • Visual Learning
  • Warning Signs
  • Weblogs
See More

January 2021

Sun Mon Tue Wed Thu Fri Sat
          1 2
3 4 5 6 7 8 9
10 11 12 13 14 15 16
17 18 19 20 21 22 23
24 25 26 27 28 29 30
31            
Mike Griffiths
Mike Griffiths

Categories

  • Agile Project Management
  • Books
  • Certification
  • Estimating
  • Events
  • Exceptions
  • Games
  • Leadership
  • Lean
  • Metrics
  • NoProjects
  • Personal Agility
  • Planning
  • PMI-ACP
  • Remote Work
  • Retrospectives
  • Risk Management
  • Tailoring Approaches
  • Teams
  • Theory of Constraints
  • Travel
  • Visual Learning
  • Warning Signs
  • Weblogs
Subscribe to this blog's feed

Your email address:


Powered by FeedBlitz

Tracker

  • Google Analytics
Blog powered by Typepad
Member since 07/2006

Archives

  • January 2021
  • December 2020
  • November 2020
  • October 2020
  • August 2020
  • July 2020
  • June 2020
  • May 2020
  • April 2020
  • March 2020

More...

  • LeadingAnswers: Leadership and Agile Project Management Blog •
  • Copyright 2006-2020 All Rights Reserved
Top